How many pounds of material are used in the current period? 5,393. 5,110. 3,500. 3,750. 4,000.

Cavern Company’s output for the current period results in a $5,250 unfavorable direct material price variance. The actual price per pound is $56.50 and the standard price per pound is $55.00. How many pounds of material are used in the current period? 5,393. 5,110. 3,500. 3,750. 4,000.


 

. .